ThoughtWorks Mingle
Technical requirements
The following requirements must be met to integrate Mingle with SD Elements.
-
Basic authentication must be enabled for Mingle.
-
A service user account is required to connect to Mingle.
-
The service account must have permission to create issues and update issue status in each target project
-
Default assigned fields
The following fields are set by default:
-
Name
-
Description
Behavior
The integration supports the following:
-
Two-way status synchronization
Connection details
Enter the connection details for the server.
Protocol |
The method to connect with the server (Default: HTTPS) |
---|---|
Server |
The domain name or IP address of the server |
Context Root |
Normally left empty unless the service is installed at a non-standard location |
Credentials
Enter the credentials needed to authenticate to the server.
Username |
Username authorized to connect with the server and having permission to create issues in anticipated Mingle projects. |
---|---|
Password |
The password used to authenticate to the server |
Tasks to Synchronize
Select tasks to synchronize.
Sync all tasks |
Synchronize all tasks from Mingle. |
---|---|
Sync Risk Policy tasks |
Synchronize only tasks that fall under the risk policy. |
Project details
Enter the project-level details.
Mingle Identifier |
The name of the project where issues should be created. |
---|
Advanced Mingle configuration
Card Type |
(Default: |
---|---|
Open a story in Mingle with the following status |
(Default: |
States which map to DONE in SD Elements: |
(Default: |
Synchronization
Enter settings for synchronizing SD Elements tasks.
Authoritative Source |
Select the tool that will be the authoritative system of record: Mingle or SD Elements. This field is used in case of conflicting statuses between the Mingle issue and the SD Elements task. When you first synchronize a TODO task in SD Elements with an issue in Mingle, they will have the same status. If you then change the status in one tool, for example by closing the issue in Mingle, they will have conflicting statuses. This conflict is resolved when the projects are synchronized. There are three options:
|
---|---|
Include code sample How-To’s in task descriptions |
Indication whether code samples are copied to Mingle |
Filter tasks
Select SD Elements tasks to synchronize to Mingle.
Tasks having a minimum priority |
Only synchronize tasks with a minimum priority, such as 7 or above. This is useful if you want to limit the amount of work for users. (Default: 1) |
---|---|
Tasks with status meaning |
Only synchronize tasks with certain statuses, such as TODO or DONE. (Default: TODO) |
Limit to tasks having these phases |
Only synchronize tasks in certain phases, such as Requirements or Development. (Default: none selected, meaning tasks from all phases will be synchronized) |
Tasks having all of the following tags |
Only synchronize tasks containing certain SD Elements task tags. (Optional) |
Tasks with verification status |
Only synchronize tasks with a specific verification status, such as Pass or Fail. (Default: none selected, meaning tasks with any verification status will be synchronized) |
Advanced ALM options
Enter advanced configuration options.
Alm context |